Approval of drawings of the electrical installation (Industrial Installations only) - Department of Electrical Inspectorate
Application for Approval of drawings of the electrical installation (Industrial Installations only) - Department of Electrical Inspectorate
Documents to be submitted with application:
1) Affidavit-8 and Form-Z
2) Power Sanction letter, Estimate and sketch
3) Electricals Drawings showing SLD, plan and elevation.
Note:- Prescribed drawing scrutiny fees shall be paid
Application Fee : NIL
Service Charge (Grama one| B1| K1) : https://ksei.gov.in/eisoft/Documents/fee-HT.pdf
ServiceTime (Days) :25 days-Head Office & 20 days Field Office Days
Electrical Installation in the jurisdiction of the state of Karnataka(Electrical Installation belonging to Government of India and its undertakings are excluded).